Jeff CSO Phase 3 Project

Construction Schedule for Restoration
Updated 05/03/2021

  • Week of 5/3/2021
    • Michigan Avenue, Spring Street (parking lane), & 7th Street – Place asphalt base
    • Wall Street – Begin roadway dig out on Wall Street between 7th Street & Court Avenue. Rivertown to follow behind with concrete restoration.
  • Week of 5/10/2021
    • Open Spring Street & 7th Street
    • Resume pipe installation on Wall Street (just North of Chestnut Street)
    • Wall Street – Continue full-width roadway dig out on Wall Street between 7th Street & Court Avenue. Rivertown will follow behind with concrete restoration.
  • Week of 5/17/2021
    • Open Wall Street between Court Avenue and Maple Street on gravel
    • Wall Street – Finish full-width roadway dig out on Wall Street between 7th Street & Court Avenue. Finish concrete restoration and place asphalt base.
  • Week of 5/24/2021
    • Open Wall Street between 7th Street & Court Avenue (traffic will be opened on asphalt base)

Note: Pipe installation is scheduled to resume next Monday, May 10th, 2021.